AR# 4344

4.2i Foundation Project Manager - My design has placed and routed/fitted successfully, but the green status checkmark does not appear in the Project Manager flow window


Keywords: check, checkmark, implementation, BIT, implemented, status

Urgency: Standard

General Description:
My design has been placed and routed or fitted successfully, but the green status checkmark does not appear on the "Implementation" icon in the Project Manager flow window.


For a green checkmark to appear in the Project Manager "Implementation" phase button, a BIT or JED file must have been created in implementation. The Project Manager does not view the phase as "complete" unless this configuration file is created and present.

If the implementation has stopped unexpectedly, check the console window for error messages. The messages should also be reflected in the $XILINX\ACTIVE\PROJECTS\ALDEC.LOG file.

For a more detailed view of the implementation status or to restart the implementation flow, select Tools -> Implementation -> Flow Engine. The Flow Engine displays the processes that have completed; it also allows you to run all processes, to run them one at a time, or to back the flow up and then rerun a process.
AR# 4344
Date Created 07/28/1998
Last Updated 08/12/2003
Status Archive
Type General Article