9.1i ISE - Project Navigator design summary is not updated for intermediate processes if Re-run is selected instead of Run

Description


The Project design summary is not updated for intermediate processes if Re-run is selected instead of Run.



Example

- A design is implemented and the Synthesis, Translate, MAP, and PAR processes are successfully completed, as indicated by a green check mark. The design summary also shows a status of "Current" for each of the process reports.

- A Translate process property is changed, which forces the Translate, MAP, and PAR processes to be out of date.

- The PAR process is re-run. The design summary continues to show a status of "Current" for each of the process reports.

- A property on Translate is changed to force the Translate, MAP, and PAR processes to be out of date.

- The Generate Post-Place & Route Simulation Model process is re-run. The design summary never shows the update event for Translate/MAP and it finally shows one event for PAR. If Run is used instead, the design summary shows all of the update events for Translate/MAP and PAR.

Solution


The design summary should immediately be updated to show a status of "Out of Date" for each of the process reports after Translate. As each process completes, the design summary should be updated to show that the status is "current" for the completed process.



Selecting Run (or simply double-clicking the desired end process) updates the design summary.